Generalcontructor and timber construction
Exetution planing: January/March
Production timber contruction: April (2 weeks)
Assambly timber contruction: Max/June (shell one store/day)
…
Basement, concret construction development
April
…
Windows, exterior door, shading
May (1 week)
…
Tinsmith roofer
May/June (2 weeks)
…
Plaster fasade
May/June (3 weeks)
…
Dry walls
May/July (5 weeks)
…
Electro / PV / power- and media distributor / unit
fire protection alarm and intercom system
May/July (4 weeks)
…
Hause technic
May/July (5 weeks)
With the latest technology from
The new heat pump a²X9, an integral total solution (heating, ventilation, hot water and coolin), optimized for highly eddicient buildings. Flexible, modular comtination options for many application variants.
…
Screed
June (2 weeks)
…
Locksmith
Tilex, painter, floors, doors
July/September
…
Tiling
company Robert Gieber
…
Carpentry
and company Markus Oberrauner
…
Glacing
…
Facilities
October-December
…